COVINGTON, Ky. – More than a dozen streets in neighborhoods across Covington will get a smoother, safer surface as part of the City’s 2025-2026 Resurfacing Project, with work scheduled to begin next week.
In total, nearly 60,000 square yards of new asphalt will be poured across 13 streets in 10 different neighborhoods: Central Business District, Botany Hills, Monte Casino, Ritte’s East, Licking Riverside, Peaselburg, Eastside, Westside, Latonia Rosedale, and South Covington.
The following streets are included in the resurfacing project:
The City is asking residents in impacted areas to be patient as work progresses. Temporary parking restrictions will be in place during paving, and affected residents have been notified by mail.
Contracts for the resurfacing were approved during the City Commission’s Legislative Meeting on July 15, 2025. The Community Development Block Grant (CDBG) Resurfacing Project will be completed by Riegler Blacktop for $290,638. The remaining Capital Resurfacing Project will be handled by Eaton Asphalt for $470,715.20.